Short answer: adding a second storey is a structural job before it is a design job. The existing footings, slab, walls and frame were sized for a single-storey house, so an RPEQ structural engineer has to confirm what they can carry, how the new loads will travel down to the ground and what must be strengthened or added. This checklist covers the structural questions to settle first, the Queensland approvals that shape the design, and what to send the engineer so the assessment starts with the right information.
It is written for homeowners, designers and builders planning to build up on an existing house in South East Queensland. It does not give costs or timeframes, because both depend on what the engineer finds in the existing structure.
Build up, raise or extend out? Know which project you have
“Going up” can mean three different things structurally, and each starts with a different check.
| Option | What changes | First structural question |
|---|---|---|
| Second storey on top of the existing house | New floor, walls and roof sit on the existing walls, posts and footings | Can the existing footings and ground-floor walls carry the extra load, and where do new posts land? |
| Raising a high-set timber house and building in underneath | House is lifted onto new stumps or columns; new rooms are built at ground level | Condition of the frame and bearers, new footing layout, bracing of the raised house |
| Two-storey addition beside or behind the house | New structure with its own footings, joined to the old house | How the new and old footings will move relative to each other at the junction |
For older high-set homes, raising is often the more practical route. Our restumping and pre-1946 house checklist covers the stump and subfloor side of that option.
The structural checklist for a second storey extension
1. Existing footings and slab capacity
- What footings exist: strip footings, a slab with edge beams, pad footings under stumps? Original plans help, but the engineer may still need to confirm sizes on site.
- Is there any sign of past movement, such as cracking, sloping floors or repaired brickwork? Movement problems get worse under extra load and must be understood first.
- Where new posts or load-bearing walls land, will they need new pad footings or local thickening of the slab?
- Is information on the site soil available? If not, the engineer may ask you to commission a site classification from a geotechnical engineer; Ostanes reviews that report but does not do soil testing.
2. The load path from roof to ground
- Which ground-floor walls are load-bearing, and can they take the new floor and roof?
- Where the upper floor plan does not line up with the walls below, transfer beams and new posts carry the load across.
- The stair opening often cuts through existing joists or a ceiling that was supporting something; trimmer beams are designed around it.
- Every new post needs a continuous path down to a footing that can take it.
3. Walls and beams on the ground floor
- Many second-storey projects also open up the ground floor. Removing a wall under a new upper level is a much bigger job than removing one under a roof alone.
- Steel or engineered timber beams are sized for the combined load, with posts and footings at each end.
- For background on beam design and wall removal, read our guide to load-bearing wall removal.
4. Upper floor, frame weight and materials
- A lightweight timber or steel-framed upper level with light cladding puts far less load on the existing house than masonry.
- Floor system choice (timber joists, engineered I-joists, steel beams) affects depth, spans and where posts are needed.
- Roof type and tie-down: a new roof higher up the site is more exposed, so the tie-down chain from roof to foundation is redesigned.

5. Bracing and wind
- A taller house catches more wind. Bracing walls are needed on both levels and must connect to each other and to the footings.
- Existing ground-floor walls may need new bracing sheets, hold-downs or strengthening where large openings are planned.
6. Junctions, levels and services
- How the new roof and walls meet the existing roof line and gutters, and how water is kept out during construction.
- Floor levels and ceiling heights: check these early, because they drive stair length and roof height.
- Plumbing stacks, downpipes and drainage that need new routes through the new structure (a plumber designs and installs those).
Queensland approvals that shape a second storey design
Brisbane City Council states that you need building approval before starting work on extensions, raising and renovations, and that a licensed building certifier assesses the building work. The certifier will rely on structural drawings and, where the design is engineered, a Form 15 design certificate from an RPEQ engineer. Points that commonly affect a second storey in South East Queensland:
- Siting and setbacks: extensions to existing houses must comply with the Queensland Development Code. Brisbane points to MP 1.1 for lots under 450 m² and MP 1.2 for lots 450 m² and over. The Queensland Development Code now includes the new Queensland Housing Code, with a transition period from 1 September 2026 to 1 September 2029, so ask your certifier which version applies in your council area.
- Planning code: in Brisbane, extensions must comply with the Dwelling house code or the Dwelling house (small lot) code, and you need planning approval if your design does not meet all acceptable outcomes. Neighbourhood plans and overlays can add criteria.
- Character houses: in Brisbane’s Traditional building character overlay, external extensions generally need planning approval, and some work to houses built during or before 1946 does as well. Council’s guidance on altering character houses lists additions that overhang the existing building or significantly change the original roof as inappropriate, and recommends building at the rear with a clear visual break. That often pushes a “second storey” on a character house towards a rear two-storey pavilion or a raise instead.
- Raising limits in the character overlay: Brisbane lists raising a house where the new height does not exceed 9.5 metres among the exemptions, and its character guidance suggests raising no more than an additional 800 mm. Council notes these exemptions can change, so check the current City Plan table with your designer or certifier.
Other councils in South East Queensland have their own planning schemes and overlays. Your designer or certifier confirms the pathway; the engineer designs the structure to suit it. Ostanes does not issue approvals.
What to send the engineer
- Existing house plans, if you have them. Many councils hold archived building plans for older properties, though not all plans survive.
- Concept or design drawings for the upper level: floor plan, elevations and the roof form.
- Photos of the outside, the subfloor (for high-set houses), the roof space and any cracks.
- Any soil or site classification report and survey plan.
- A note of ground-floor walls you would like to remove or open up.
- Your certifier’s name, if you have one, so the documents match their requirements.
With these, an Ostanes RPEQ engineer can tell you whether the existing structure is a realistic base, what extra investigation is needed, and then design the footings, beams, framing, bracing and tie-down for the new level. Our extension structural engineering service explains the design and Form 15 documentation in more detail.
Warning signs that change the plan
- Existing cracking or floor movement that has not been explained.
- Stumps, bearers or wall frames with decay, termite damage or past poor repairs (a licensed pest inspector reports on termites; the engineer assesses the structural effect).
- Earlier alterations, such as removed walls or enclosed verandahs, with no approval record.
- Very shallow or undersized footings found during investigation.
None of these automatically rules out a second storey, but each one needs to be resolved in the design rather than discovered by the builder. If your plans also involve broader internal changes, our renovation structural engineering page covers how alterations to existing load paths are handled.
Second storey extension: common questions
Can any house take a second storey?
Not without checking. Some houses can take a lightweight upper level with local strengthening; others need new footings throughout, and some are better suited to raising or a two-storey addition at the rear. The existing footings and frame decide which.
Is a lightweight second storey extension easier structurally?
Usually, because a lighter frame and cladding add less load to the existing footings and walls. It still needs a designed load path, bracing and tie-down, and wind exposure increases with height.
What drives the structural side of a second storey’s cost?
Mainly the condition and capacity of the existing footings, how much of the ground floor has to be strengthened or opened up, and whether new posts and footings are needed inside the house. We do not publish prices; the engineer can scope the design once the existing structure is understood.
Do I need a Form 15 for a second storey?
Where the structure is engineered, the certifier will normally ask for structural drawings and a Form 15 signed by an RPEQ engineer. The certifier decides what documentation the approval needs.
Plan the structure before the floor plan is fixed
The cheapest time to solve a load path problem is before the design is finalised. Send us your plans and photos and an RPEQ engineer will review whether your house can take a second storey and what needs to be checked first.